Chapter 2

Installation

Preparation

1.

Test the existing SCS control system to ensure all product control hardware is operating properly. Repair or
replace any faulty components of the product control system before proceeding.

2.

Copy the calibration values from the existing SCS console.

Note:

Calibration Values are stored on the existing SCS console and must be programmed into the new
product control console before the Switch Pro system is ready to operate. The following values are
required for Switch Pro operation:

Speed cal

Boom cals for each configured boom section on the existing SCS control system

The following are required for each product:

Meter cal or product density

Valve type

Valve cal

Rate cal(s)

Spreader constant (granular systems)

3.

Verify that the existing SCS console cable has been installed properly. Refer to the Best Wiring Practices
section on page 8 se
ction later in this chapter for more information.

If an existing Raven SCS 440, 450, 4400 system has not previously been installed prior to purchase of the
Switch Pro system, additional cabling and hardware will be required when installing the Switch Pro system.
Please contact a local Raven dealer for specific flow control components required and installation
assistance.

4.

Disconnect the SCS console from the console cable and remove from cab.

5.

Remove any existing auxiliary section switches.

Note:

If existing section switch hardware cannot be removed, the auxiliary section switches must be in
the Off position to allow Switch Pro to operate properly.

If a Remote Master Switch will be used with the Switch Pro, both master switches must be in the
Off position to turn off booms. Toggling either the Switch Pro master or the remote master will
enable boom sections.

6.

Remove any mounting hardware or brackets for the existing SCS control console. The machine is now
ready for installation of the Switch Pro system.