Commissioning – REMKO FBR-2 User Manual
Page 9

9
Commissioning
Commissioning should only be
performed and documented by
specially trained personnel.
NOTE
The following steps must be followed
when commissioning:
1. Read this manual carefully before
commissioning.
2. Remember that the resistance of
the connection cable influences
the nominal setting and room
temperature measurement.
For example, a cable with 0.25 mm
2
cross section (telephone wire) and
10m in length causes a nominal
value increase of 2K and a reduction
in room temperature measurement
of 0.01K.
3. Check the resistance at the next
measure point shown.
4. Compare your measurement with
the table given, taking into account
the room temperature.
Test points
Room
temperature in °C
Resistance
in Ohms
+ 10°C
9.950 Ω
+ 15°C
7.855 Ω
+ 20°C
6.245 Ω
+ 25°C
5.000 Ω
+ 30°C
4.028 Ω