beautypg.com

Installation evaporative cooler piping (optional), Warning, Important – Greenheck DG / DGX with Direct Spark (470652) User Manual

Page 9: Caution, Install the drain line, Check/adjust water level, Test the system for leaks, Pipe the optional vent line

background image

Direct Spark Ignition Make-Up Air

9

®

Optional Vent Line

WARNING

NEVER test for a gas leak with an open flame.

NOTE

The factory piping has been checked for leaks, but
should be rechecked due to shipping and installation.

WARNING

Reference the National Fuel Gas Code for additional
vent line requirements.

Installation Evaporative Cooler
Piping (optional)

IMPORTANT

All supply solenoids, valves and all traps must be below
the roof line or be otherwise protected from freezing.

IMPORTANT

The supply line should be of adequate size and
pressure to resupply the amount of water lost due to
bleed-off and evaporation. The drain line should be
the same size or larger than the supply line.

CAUTION

Provisions must be taken to prevent damage to
the evaporative cooling section during freezing
conditions. The sump, drain lines and supply lines
must be drained prior to freezing conditions or an
alternate method must be used to protect the lines
and media.

Evaporative Cooling with Recirculating Pump

1. Install the Water Supply Line

Supply line opening requirements vary by unit size and
arrangement and are field-supplied. Connect the water
supply line to the float valve through the supply line
opening in the evaporative cooling unit. Install a manual
shutoff valve in the supply line as shown above.

2. Install the Drain Line

Connect an unobstructed drain line to the drain and
overflow connections on the evaporative cooler. A
manual shut off valve (by others) is required for the
evaporative cooler
drain line.

A trap should be used
to prevent sewer gas
from being drawn
into the unit. Refer to
drain trap diagram.

3. Check/Adjust Water Level

Check the water level in the sump tank. The water
level should be above the pump intake and below the
overflow. Adjust the float as needed to achieve the
proper water level.

Recirculating Evaporative Piping

6 in. min.

6 in. min.

Drain

Trap

5. Test the System for Leaks

Check both the supply lines and the factory piping for
leaks. Apply a soap and water solution to all piping and
watch for bubbling which indicates a leak.

4. Pipe the Optional Vent Line

If an optional vent line is located between the safety
shutoff valves, it must be piped to the outdoors.

Vent Line Solenoid

Safety Shut-Off Valves

to burner

to outdoors

from supply

V

ent Line

Supply Line

Overflow

Trap

Drain Line

Supply Line Valve

Drain Line Valve