Flowserve DDC-100 Modbus Direct-to-Host User Manual
Page 31
![background image](https://www.manualsdir.com/files/784794/content/doc031.png)
56
DDC-100 Direct-to-Host Programming Guide
FCD LMAIM4019-00
FCD LMAIM4019-00
DDC-100 Direct-to-Host Programming Guide
57
Contractor Tasks
Deliverable
From
To
Comments
Specifications
Engineer
Contractor
Complete P&IDs for site
Schedule
Engineer
Contractor
Time line complete w/milestones
Project Responsi-
bilities
Engineer
Contractor
Define which supplier is responsible for each
portion of project
P&ID
Engineer
Contractor
Detailed layout and instructions for building
site. Information should include actuator tag
names, required data points from actuator,
field unit, and field wiring
Site Electrical
and electronics
Engineer
Contractor
Detail site electrical requirements, cable type,
layout, and locations. Voltages available for
equipment
Loop Drawings
Engineer
Contractor
Detail cable routings from Host to each field
device. This defines how the network cable is
to run throughout the facility
Schedule
Contractor
Limitorque
Provide material delivery dates for hardware.
Schedule Flowserve Limitorque Controls
Service Technician for actuator commis-
sioning (when requested according to
purchase order)
Hardware
Limitorque,
OEM
Contractor
Provide Motor-Operated Valves, RS-232/485
converters (if supplied), valves, mounting
adapters, etc.
Manuals
Limitorque
Contractor
Product Bulletins for Actuators:
• LMAIM4019 Direct-to-Host Programming
Guide
• LMAIM1329 Accutronix Installation and
Operation for MX-DDC Field Unit
• LMAIM4029 DDC-100 UEC Field Unit
(Modbus) Installation and Operation Manual
• LMAIM4030 DDC-100 UEC Field Unit Instal-
lation and Commissioning Manual
• LMAIM4022 DDC-100 UEC Field Unit
Wiring and Startup Guidelines
• Modicon Modbus Protocol Reference Guide
PI-MODBUS-300 Rev. G (available from
Modicon)
Operational System
S.I.
Contractor
Develop and test programming for DCS
system
Documents
S.I.
Contractor
Documentation of program operational char-
acteristics, equipment used, and Operation
and Maintenance Manuals for equipment
Schedule
Contractor
S.I.
Provide delivery dates for commissioning
control system. Include dates for testing,
documentation, and turnover to site personnel
Hardware for
system development Contractor
S.I.
Hardware may include: DDC-100 Field Units,
RS-232/485 converters
Actuator
Contractor
S.I.
Availability of DDC-100 Field Unit for testing
developed application software
Site Preparation
Contractor
S.I.
Complete actuator or field unit installation.
Provide actual (as installed)
Site Preparation
Contractor
Limitorque
Install specified equipment, cables for
power and network communication. Verify
all network and power cables are properly
routed, terminated, and documented prior
to commissioning of DDC-100 Network. The
contractor should provide detail on network
routing from Host system to each field unit.
Verify all field units are properly grounded
Field Unit Startup
Limitorque
Contractor
According to purchase order requirements,
when scheduled
Limitorque Tasks
Deliverable
From
To
Comments
Specifications
Engineer
Limitorque
Provide specification on Motor-Operated
Valves, other DDC-100 Field Units (I/O
Modules). Provide P&IDs
Schedule
Contractor
Limitorque
Provide material delivery dates for hardware.
Schedule Flowserve Limitorque Controls
Service Technician for actuator commis-
sioning
Site Preparation
Contractor
Limitorque
Install specified equipment, cables for
power, and network communication. Verify
all network and power cables are properly
routed, terminated, and documented prior
to commissioning of DDC-100 Network. The
contractor should provide detail on network
routing from Host system to each field unit.
Verify all field units are properly grounded
Operational
S.I.
Limitorque
Provide unique field unit requirements to
Controls Service Technician Requirements
prior to start of field unit commissioning
process. Include: ESD requirements, open/
close service or position control (“move-to”),
digital inputs/outputs, analog inputs
Tag List
S.I.
Limitorque
Provide a tag list detailing valve tag name
to network address. This will allow the
Limitorque Controls Service Technician
(when requested according to purchase
order) to properly address the actuators to
the developed Host software
Sales Support
Limitorque
Engineer
Information on Limitorque products
Manuals
Limitorque
S.I.
Engineer
Contractor
Product Bulletins for Actuators:
• LMAIM4019 Direct-to-Host Programming
Guide
• LMAIM1329 Accutronix Installation and
Operation for MX-DDC Field Unit.
• LMAIM4029 DDC-100 UEC Field Unit
(Modbus) Installation and Operation Manual
• LMAIM4030 DDC-100 UEC Field Unit Instal-
lation and Commissioning Manual
• LMAIM4022 DDC-100 UEC Field Unit
Wiring and Startup Guidelines
• Modicon Modbus Protocol Reference Guide
PI-MODBUS-300 Rev. G (available from
Modicon)
Hardware
Limitorque,
Contractor
Provide Motor-Operated Valves, RS-232/485
converters (if supplied), OEM valves,
mounting adapters, etc.
Field Unit Startup
Limitorque
Contractor
According to purchase order requirements,
when scheduled