It is the plant operator's responsibility to
ensure that all maintenance, inspection and 
assembly work is carried out by authorized and 
qualified personnel who have adequately 
familiarized themselves with the subject matter by 
studying this manual in detail (see also section 
1.6.2). 
Any work on the machine must be performed when 
it is at a standstill. It is imperative that the 
procedure for shutting down the machine is 
followed, as described in section 5.6. 
 
On completion of work all guards and safety 
devices must be re-installed and made operative 
again. 
 
Before restarting the machine, the relevant 
instructions listed in section 5, Commissioning, 
start up, operation and shut down must be 
observed.
An oil, grease or liquid leakage may make the 
ground slippery. The maintenance of a 
machine must always begin and finish by 
cleaning the ground and the exterior of the 
machine. 
If platforms, stairs and guardrails are required for 
maintenance, they must be placed for easy access 
to areas where maintenance and inspection are to 
be carried out. The positioning of these 
accessories must not limit access or hinder the 
lifting of the part to be serviced. 
When air or compressed inert gas are used to 
clean the machines, the operator and those people 
in the vicinity must be careful and have appropriate 
gas-protection, wearing at least eye protectors. DO 
NOT SPRAY air or compressed inert gaz on skin. 
DO NOT DIRECT an air or gas jet towards other 
people. Never use air or compressed inert gas to 
clean clothes. 
Before working on the pump, take measures to 
prevent an uncontrolled start. Put a warning board 
on the starting device with the words: 
"Machine under repair: do not start". 
With electric drive equipment, lock the main switch 
open and withdraw any fuses. Put a warning board 
on the fuse box or main switch with the words: 
"Machine under repair: do not connect". 
Never clean pieces with inflammable solvents or 
carbon tetrachloride. Protect yourself against toxic 
fumes when cleaning pieces with cleaning agents. 
6.2 Maintenance schedule
It is recommended that a maintenance plan
and schedule is adopted, in line with these User 
Instructions. It should include the following: 
a) The pump must be completely vented and 
drained and rendered inert before any 
disassembly operation. 
b) Any auxiliary systems installed must be
monitored, if necessary, to ensure they 
function correctly. 
c) During cleaning of the pump ensure the
compatibility between the cleaning products 
and the gaskets. 
d) Verify the condition of the gaskets 
e) Gland packings must be adjusted correctly to 
give visible leakage and concentric alignment 
of the gland follower to prevent excessive 
temperature of the packing or follower. 
Mechanical seals should present no leakage. 
f) Check for any leaks from gaskets and seals.
The correct functioning of the shaft seal must 
be checked regularly. 
g) Check bearing lubricant level, and if the hours
run show a lubricant change is required.
h) Check that the duty condition is in the safe
operating range for the pump.
i)
Check vibration, noise level and surface 
temperature at the bearings to confirm 
satisfactory operation. 
j)
Check the tightness of the connections.
k) Check dirt and dust is removed from areas
around close clearances, bearing housings 
and motors. 
l)
Check coupling alignment and re-align if 
necessary. 
m) Verify the correct operation of the system.
The equipment used for maintenance and 
disassembly in an ATEX zone must be in 
conformity with the requirements zone. 
Our specialist service personnel can help with 
preventative maintenance records and provide 
condition monitoring for temperature and vibration 
to identify the onset of potential problems. 
If any problems are found the following sequence 
of actions should take place: 
a) Refer to section 7, Faults; causes and 
remedies, for fault diagnosis.
b) Ensure equipment complies with the
recommendations in this manual.
c) Contact Flowserve if the problem persists.
6.2.1 Standard maintenance
Roller bearing
The bearings fitted are prepacked with grease at 
the factory. When the regreasing period is reached 
it is necessary to remove as much of the old 
grease as possible with a clean lint free cloth and 
repack the bearings with fresh grease. 