Glow-worm EnergySaverCombi 100 User Manual
Page 17
17
221854B
Boiler Fixing
Having previously secured the wall mounting jig and hanging
bracket to the wall, lift the boiler into position in the following
manner. To assist in the lifting of the boiler, remove the front
panel.
Lean the top of the boiler slightly to the wall and position just
above the hanging bracket. Allow the boiler to slowly move
downwards until engaged in the hanging bracket.
Slowly swing the base of the boiler to the wall mounting jig
ensuring that the copper tails on the boiler fit into the gas and
water isolation valves on the jig, see diagram 8.1. If necessary
the gas and water isolation valve clamps can be loosened to
ease fitting. Make sure that the isolation valves are secured
with the clamps after making good the connections.
Connect the two electrical connector plugs hanging from the
boiler into the sockets on the wall mounting jig. The white mains
electrical supply socket on the left hand side of the jig and the
black auxiliary electrical socket on the right hand side of the jig.
Please refer to condensate connection before proceeding,
see section 9.4.
Attach the flue as described in section 7.6.
BOILER
MOUNTING
FRAME
GAS
ISOLATION
VALVE
Diagram 8.1
CENTRAL
HEATING
RETURN
DOMESTIC
HOT
WATER
OUT
CENTRAL
HEATING
FLOW
DOMESTIC
COLD
WATER
SUPPLY IN
9056
DRAIN
POINT
DRAIN
POINT
GAS
SERVICE
COCK
ALL SLOTS SHOWN IN
CLOSED POSITION
CLAMP
SECURING
SCREW
PRESSURE RELIEF
VALVE PIPE
GAS & WATER ISOLATION VALVES
8 Boiler Fixing
9 Gas, Water, and Condensate Connections
9.1 Gas Connection
The gas supply can be connected from below or through the
wall at the rear of the boiler, the position is shown on the wall
template.
Refer also to section 1.2.
Make the gas supply connection to the gas isolation valve.
Slacken or remove the clamp, as desired, whilst making the
connection. Do not subject the gas isolation valve to heat, see
diagram 8.1.
9.2 Water Connections
Provision is made for the water connections to be made from
below or through an internal wall at the rear of the boiler, the
position is shown on the wall template. Copper tail pieces are
supplied in the wall mounting pack if required.
Flush out the domestic hot water and the heating systems
before connecting to the boiler.
Make the connections to the domestic hot water and heating
systems by way of the isolating valves, see diagram 8.1
Slacken or remove the clamps, as desired, while making the
connections. Do not subject any of the isolating valves to heat.
DOMESTIC
WATER
VALVES
CENTRAL
HEATING
VALVES
DRAIN
POINT TO
FRONT OF
APPLIANCE