Location and support, Generator compartment, Cooling and ventilating air – Generac Power Systems 00862-2 User Manual
Page 36: Gasoline fuel system, Optional lp gas fuel system, Exhaust system, Electrical connections, Battery installation, Optional accessories, Post installation tests
Attention! The text in this document has been recognized automatically. To view the original document, you can use the "Original mode".

TROUBLESHOOTING
Section 4 - Troubleshooting
Series QP55-G Recreational Vehicle Generator
4.1 INSTALLATION CHECKLIST
♦
LOCATION AND SUPPORT_______________________
□ Generator is properly located.
□ Generator is properly supported.
□ Generator is properly restrained.
♦
GENERATOR COMPARTMENT ____________________
□ Compartment construction is proper.
□ Holes/Openings are vapor-sealed.
□ Compartment size is correct.
□ Compartment is vapor-sealed.
□ Sound insulation is correct.
□ Floor cutouts are properly completed.
♦
COOLING AND VENTILATING AIR
□ Airflow is adequate.
□ Air inlet opening is correct.
□ Compensate for restrictions.
□ Check that installation has been tested.
♦
GASOLINE
FUEL SYSTEM_______________________
□ Fuel tank complies with all applicable codes.
□ Fuel system is properly installed and checked
for leaks.
♦
OPTIONAL LP GAS FUEL SYSTEM
□ Fuel system is properly installed and checked
for leaks.
□ Pressure at regulator inlet is correct.
□ Rated flow of primary regulator is correct.
□ All parts are properly installed.
□ Fuel system is properly tested/adjusted.
♦ EXHAUST
SYSTEM
□ Exhaust system complies with all applicable
codes.
□ Exhaust system is properly and safely installed.
♦ ELECTRICAL
CONNECTIONS
□ Connections comply with local code require
ments and all National Electrical Codes.
□ Junction box is properly installed.
□ Wiring meets all standards.
□ All connections are correct.
□ Conduit is properly Installed and sealed.
□ Generator is properly bonded to the vehicle.
♦ BATTERY INSTALLATION
□ Recommended battery is installed.
□ Recommended cables are installed.
□ Cables are clean and tight.
□ Cables are connected properly.
□ Proper ventilation is provided.
□ Terminals are coated with anti-corrosion grease,
and terminal covers are positioned.
♦ OPTIONAL ACCESSORIES
□ Check that remote start/stop panels (if used) are
installed properly.
□ Check that hourmeter kit (if used) is installed
properly.
□ Check that any other options and accessories (if
used) are installed properly.
♦ POST INSTALLATION TESTS
□ Check that all tests are completed properly.
DATE OF INSTALLATION
NAME OF INSTALLER
SIGNATURE OF INSTALLER
3^1 Generac* Power Systems, Inc.