TROUBLESHOOTING

Section 4 - Troubleshooting

Series QP55-G Recreational Vehicle Generator

4.1 INSTALLATION CHECKLIST

LOCATION AND SUPPORT_______________________

□ Generator is properly located.

□ Generator is properly supported.

□ Generator is properly restrained.

GENERATOR COMPARTMENT ____________________

□ Compartment construction is proper.

□ Holes/Openings are vapor-sealed.

□ Compartment size is correct.

□ Compartment is vapor-sealed.

□ Sound insulation is correct.

□ Floor cutouts are properly completed.

COOLING AND VENTILATING AIR

□ Airflow is adequate.

□ Air inlet opening is correct.

□ Compensate for restrictions.

□ Check that installation has been tested.

GASOLINE

FUEL SYSTEM_______________________

□ Fuel tank complies with all applicable codes.

□ Fuel system is properly installed and checked

for leaks.

OPTIONAL LP GAS FUEL SYSTEM

□ Fuel system is properly installed and checked

for leaks.

□ Pressure at regulator inlet is correct.

□ Rated flow of primary regulator is correct.

□ All parts are properly installed.

□ Fuel system is properly tested/adjusted.

♦ EXHAUST

SYSTEM

□ Exhaust system complies with all applicable

codes.

□ Exhaust system is properly and safely installed.

♦ ELECTRICAL

CONNECTIONS

□ Connections comply with local code require­

ments and all National Electrical Codes.

□ Junction box is properly installed.

□ Wiring meets all standards.

□ All connections are correct.

□ Conduit is properly Installed and sealed.

□ Generator is properly bonded to the vehicle.

♦ BATTERY INSTALLATION

□ Recommended battery is installed.

□ Recommended cables are installed.

□ Cables are clean and tight.

□ Cables are connected properly.

□ Proper ventilation is provided.

□ Terminals are coated with anti-corrosion grease,

and terminal covers are positioned.

♦ OPTIONAL ACCESSORIES

□ Check that remote start/stop panels (if used) are

installed properly.

□ Check that hourmeter kit (if used) is installed

properly.

□ Check that any other options and accessories (if

used) are installed properly.

♦ POST INSTALLATION TESTS

□ Check that all tests are completed properly.

DATE OF INSTALLATION

NAME OF INSTALLER

SIGNATURE OF INSTALLER

3^1 Generac* Power Systems, Inc.