START UP PROCEDURE

Engine Generator Set only

The engine control module (ECM) is manufactured

by Deep Sea Electronics. Model 30 is used on

this engine generator set. See picture below. Ad-

ditional information on the DSE 30 is on pages 4,

9-2.

Manual Operation

Press and release the red

Stop/Reset button. Then

press and release the green

Start Engine button.

The engine generator will crank and start automati-

cally. If the engine fails to start see Fault Codes on

page 20 to correct the problem before proceeding.

With the engine running smoothly, check the no load

voltage and frequency at wire # and # 4 (L2 and

L6 in the ASCO ATS) on the generator terminal block

in the ATS. The voltage should be 240 volts plus or

minus nominal. The frequency should be between

6.5 to 62 hertz (Hz). The voltage should also be

checked between the hot terminals (L2 and L6) and

the neutral to be certain of a balanced voltage output

and a solid neutral connection. The voltage should

be about on half of the line to line voltage. See pic-

ture below for frequency adjustments.

** NOTICE **

If for any reason during the check out procedures

the voltage and frequency are not correct, press the

red

Stop/Reset button and correct the trouble before

proceeding.

After verifying the voltage and frequency are correct,

press the

Stop/Reset button. This will shut off the

engine immediately.

BEND THIS TAB TO CHANGE THE ENGINE SPEED (FREQUENCY).

STRETCHING SPRING INCREASES THE FREQUENCY (INCREASES ENGINE

SPEED).

RELAXING SPRING DECREASES THE FREQUENCY (DECREASES ENGINE SPEED).