beautypg.com

Dc electrical interconnection, Initial start up – Winco ULPSS15B2W/E User Manual

Page 13

background image

3

088-00

60706-207

DC ELECTRICAL

INTERCONNECTION

**** CAUTION ****

Never run the AC and DC wiring in the same con-

duit.

ASCO 185 UL SWITCH

Your DC connection points in the ASCO 85 UL ATS

are on the terminal block on the bottom of the con-

troller in the lower left hand corner of the ATS panel.

The terminal block (TB7) is numbered through

9. These terminals will accept # 22 - # 4 AWG

stranded wire. It is recommended that you use # 6

AWG for distances up to 200 feet. You need to run

two (2) wires from the engine generator set to the

transfer switch. You will be using terminals 4 and 5,

wire Start # 23 will connect to terminal # 5 and wire

Battery Negative # will connect to terminal # 4.

See table and illustration below.

WIRE #

PURPOSE

RECOMMENDED

COLOR

# 23

Start

Black

# 1

Battery Negative

White

INITIAL START UP

******************

***** WARNING *****

******************

DO NOT jump start these engine generator sets.

Starting these units on a low battery of jump start-

ing them will cause damage to the engine control

module.

Use the following checklist to verify correct in-

stallaion before starting the engine:

Engine oil.* Check level & fill as required with

proper grade/quantity.

Unit mounting base properly bolted down.

Clearance for service and maintenance on all

sides.

Proper fuel line material and size.

All fuel line connections tight.

Fuel line protected and a moisture trap in

stalled (may be required for NG).

LP/NG pressure OK. 4-6 oz. (7- in. WC).

Battery connections clean and tight.

Battery fully charged.

All AC and DC wiring installed and properly

protected.

* Refer to engine owners manual for proper

levels and types.

After completing the above checklist, the engine

generator set is ready for the initial start-up test.