4

60706-209

. Turn on the preferred source (utility) circuit

breaker. The utility source acceptable light should

now come on as well as the transfer switch on utility

light. If these lights fail to come on recheck your

incoming power to insure you have 240 volts nomi-

nal. If not, troubleshoot your utility source before

continuing.

******************

***** WARNING *****

******************

PERSONAL INJURY HAZARD - Install front cover

in transfer switch before operation. An electrical sys-

tem fault could cause a flash and severe personal

injury.

2. Press and release the

Auto button on the

engine control module (ECM). The auto mode icon

will appear on the screen. The unit is now ready to

be operated from the Automatic Transfer Switch.

3. Turn on the altenate source (generator) curcuit

breaker.

There are two ways to test your transfer switch

operation: WITHOUT a load transfer or WITH a

load transfer.

WITHOUT load transfer (normal exercise)

. Press and release the

Push to Test button.

The generator set should start immediately. About

5 seconds the generator (alternate source) accept-

able light comes on and stays on.

2. The generator set runs for 20 minutes. The

Transfer Switch does not transfer the load to the

generator set. The

Transfer Switch on utility (pre-

ferred source) light stays on.

3. To bypass the time delay or cancel the test,

press and release the

Push to Test button again.

4. The generator set stops and the

Generator

acceptacle light goes off.

WITH Load Transfer

. Press and hold the

Push to Test button until

the generator (alternate source) acceptable light

comes on and stays on. Then release the button.

This will start up your generator set.

This light indicates that the generator is running and

the output voltage and frequency are within accept-

able limits. Under normal conditions this light should

come on in 5 to 0 seconds. If the light does not

come on and stay on a malfunction has occurred.

Either the unit didn’t start or the voltage or frequency

is incorrect. Correct the problem before continuing.

2. About 5 seconds after the generator (alter-

nate source) acceptable light comes on, the auto-

matic transfer switch should transfer the load from

the utility to the generator. At that time the Transfer

Switch

generator acceptable light should come on.

3. The generator will stay connected to the load

for about 5 minutes at which time the transfer switch

will transfer the load back to the utility. At the time it

transfers back to utility the Transfer Switch on Utility

light should come on and the Transfer Switch on

generator light should go out. To bypass this five

minute time delay you can press and release the

Push to Test button again at any time.

4. After the load retransfer to the utility, the gen-

erator will continue to run for about minute (without

a load) and then shut down. The Generator accept-

able light will go off indicating the generator set has

shut down.

This completes the functional test of the transfer

switch and the generator set. If you want the gen-

erator to automatically start press the

Auto button

on the engine control module of the generator set. If

you have additional work to do or don’t want to leave

the engine generator set in the automatic start mode

press and release the

stop/reset button on the gen-

erator set. In the off mode the engine generator set

will not start or run automatically.

GENERATOR EXERCISER CIRCUIT

The automatic generator exerciser is configured to

automatically exercise the generator for 20 minutes

once every 4 days.