13. CONNECTION INSPECTION

13.1. Inspection of Connections and Wiring

• After all connections are completed, inspect the connections and wiring again before turning on the AC

breaker of Junction Panel JP-0410.

• Ensure that cables are correctly connected between components. Also, check external wiring for connection

errors and wiring omissions.

13.2. Adjustment and Measurement of Power Circuitry

13.2.1. AC line insulation measurement (using megger)

Disconnect the power cable connection to measure the insulation between the following items.

(1) Between the ground and one line (Between G and L1) : Over 0.1 M

(2) Between ground and another line (Between G and L2) : Over 0.1 M

(3) Between lines (Between L1 and L2)

: Over 0.1 M

When lowering 0.1 M

Ω, check for flaws on cable sheath, defective taping in the joint box, and any leakage into

pipes. If such problems are found, repair immediately.

13.2.2. Power voltage measurement (using tester)

Measure voltage between lines. Normally, it must be within the range between –5% and +10% of nominal
voltage.
• When lowering –5% of nominal voltage, the power capacity is insufficient. Inspect and adjust the receiving

system.