1. Test the functionality of the original
manufacturer’s boom controls. The
NORAC Control Panel (E01) does not
need to be powered up for the original
switches to function. Unfold the booms
and raise/lower each boom and main
section. Confirm that the cabling and
hoses are agreeable to the entire range
of motion. If one or more of these
functions do not work, review the
hydraulic and electrical portions of this
manual to check for proper installation.
2. Unfold the booms and level to 90 cm
(or 35 inch) nozzle height. At this point
ensure the UC4+ sensors are reading
from an adequate and uniform target,
such as gravel or dirt.
3. By using the “Quick Install” feature of
the UC4+ panel, the system may be
configured in preparation for the End-
User. However, a hydraulic “ReTune”
procedure will be required for optimal
performance. This is required to tune
the UC4+ hydraulic parameters to
those of the End-User tractor hydraulic
system.
4. To perform the “Quick Install”
procedure, select the MS1 sprayer
type. However, rather than toggling
“YES” to select the MS1 type, hold the
toggle switch towards “YES” (for
several seconds) until the word
“SENSOR” appears on the UC4+
control panel screen.
5. The UC4+ control panel will then
prompt the installer to “EXIT CAB
AND PUSH BOOM TIP DOWN
TO GROUND”. When exiting the
cab and approaching the boom, avoid
walking near the sensors as this may
result in measurement error.
6. From the left or right boom tip, pull the
boom down approximately two feet and
release it. This will calibrate the roll
sensors.
7. At this point the UC4 panel should
display the Main Operating Screen:
M 90
M
(example)
8. This indicates the system is ready for
the second stage of installation. This will
be carried by the end user (for the
reasons as described previously in Step
3).