beautypg.com

Step 1-provide unit support, Step 2 - field fabricate ductwork – Carrier 50HE003-006 User Manual

Page 2

background image

2

Step 1

—Provide Unit Support

Roof Curb
Assemble and install accessory roof curb in accordance with

instructions shipped with curb. (See Fig. 2.) Install insulation,

cant strips, roofing felt, and counter flashing as shown. Ductwork
must be attached to curb, not to the unit.
If electric control power

or gas service is to be routed through the basepan, attach the
accessory thru-the-bottom service connections to the basepan in

accordance with

the accessory

installation instructions.

Connections must be installed before unit is set on roof curb.

C06108

Fig. 1

--- Horizontal Conversion Panels

IMPORTANT: The gasketing of the unit to the roof curb is critical
for a watertight seal. Install gasket supplied with the roof curb as
shown in Fig. 2. Improperly applied gasket can result in air leaks and
poor unit performance.
Curb should be level. Unit leveling tolerances are shown in Fig.
3. This is necessary for unit drain to function properly. Refer to

Accessory Roof Curb Installation Instructions for additional
information as required.

Slab Mount (Horizontal Units Only)

Provide a level concrete slab that extends a minimum of 6 in.

beyond unit cabinet. Install a gravel apron in front of
condenser-coil air inlet to prevent grass and foliage from

obstructing airflow.

NOTE: Horizontal units may be installed on a roof curb if
required.
Alternate Unit Support
When the curb or adapter cannot be used, support unit with
sleeper rails using unit curb or adapter support area. If sleeper

rails cannot be used, support the long sides of the unit with a

minimum of 3 equally spaced 4-in. x 4-in. pads on each side.
Step 2

—Field Fabricate Ductwork

Secure all ducts to roof curb and building structure on vertical

discharge units. Do not connect ductwork to unit. For horizontal

applications, field-supplied isolation flanges should be attached to
horizontal discharge openings and all ductwork should be secured

to the flanges. Insulate and weatherproof all external ductwork,
joints, and roof openings with counter flashing and mastic in

accordance with applicable codes.
Ducts passing through an unconditioned space must be insulated
and covered with a vapor barrier.
If a plenum return is used on a vertical unit, the return should be
ducted through the roof deck to comply with applicable fire

codes.
A minimum clearance is not required around ductwork. Cabinet

return-air static pressure (a negative condition) shall not exceed

0.35 in. wg with economizer or 0.45 in. wg without economizer.
Step 3

—Install External Trap for

Condensate Drain
Condensate drain connections are located on the bottom and side

of the unit. Unit discharge connections do not determine the use
of drain connections; either drain connection can be used with

vertical or horizontal applications.
When using the standard side drain connection, ensure the plug

(Red) in the alternate bottom connection is tight before installing
the unit.
To use the bottom drain connection for a roof curb installation,

relocate the factory-installed plug (Red) from the bottom
connection to the side connection. The center drain plug looks

like a star connection, however it can be removed with a

1

/

2

-in.

socket drive extension. (See Fig. 4.) The piping for the

condensate drain and external trap can be completed after the unit

is in place.
All units must have an external trap for condensate drainage.

Install a trap 4-in. deep and protect against freeze-up. If drain line
is installed downstream from the external trap, pitch the line away

from the unit at 1 in. per 10 ft of run. Do not use a pipe size

smaller than the unit connection (

3

/

4

in.). (See Fig. 5.)

50H

E,

H

J

This manual is related to the following products: