Reliance Controls Pro/Tran Q Series User Manual

Page 10

background image

Certain models have color-coded wire leads instead of a terminal block. Connect the wire
leads to the remote power inlet box using the same color key as used for wiring the terminal
block above (see Figure 5).

Models with suffix -A, -AE, and -B can be hard-wired by removing the power inlet and
connecting the wire leads as described in the preceding paragraph. Install the plastic
cover included with the unit over the inlet opening after the inlet is removed.

Models with Analog Wattmeters (suffix -A and -C). Most of these models are factory
pre-wired. When connecting an analog watt meter equipped transfer switch to either a
power inlet or power inlet box, run
the black wire lead going to the inlet
through the hole in the current
transformer (the small black
doughnut-shaped device) attached
to the left hand meter. Run the red
wire lead through the hole in the
current transformer attached to the
right hand meter. No direct
connection to the meter is
necessary for the meters to function
as described on the bottom of page
2.

Models with Electronic Meter (suffix -AE and -CE). These models are factory prewired
at the terminal block located on the bottom wiring compartment cover.

Completing the Installation

When you have wired all the load circuits in the transfer switch, only the white neutral wire
and the green ground wire remain.
1. Insert the white neutral wire into an unused opening in the neutral bar in the load

center and tighten the screw (Figure 4).

2. Insert the green ground wire into an unused opening in the ground bar, if existing, and

tighten the screw. If no ground bar exists, insert the green wire into an unused hole in
the neutral bar and tighten the screw.

3. Replace the cover to the load center.
4 Fill in the chart on the transfer switch to identify your emergency circuits and

corresponding circuit numbers in the load center.

5 Return all load center branch circuit and main breakers to the "ON" position.
6 Move all circuit selector switches on the transfer switch to the

"LINE" position.


Installation is now complete.