Connecting the fc san module to the fabric – Dell POWEREDGE M1000E User Manual
Page 10
8
Dell 8/4Gbps FC SAN Module Getting Started Guide
53-1001963-01
Connecting the FC SAN Module to the fabric
NOTE
on page 4 before beginning the following procedure.
Perform the following steps to connect the FC SAN Module to the fabric.
1.
If you need to install SFP transceivers, install them in the external Fibre Channel ports as required.
a.
Remove the dust plugs from the ports to be used.
b.
If necessary, remove the end caps from the SFP.
c.
Orient the transceiver correctly and insert it into a port until it is firmly seated and the latching mechanism
clicks.
For instructions specific to the type of transceiver, refer to the transceiver manufacturer’s documentation.
d.
Repeat substeps a, b, and c for the remaining ports, as required.
NOTE
Use only Dell-approved SFPs
on the external ports of this module.
2.
Connect the cables to the transceivers.
The transceivers are keyed to ensure correct orientation. If a transceiver does not install easily, ensure that it is
correctly oriented and that the end caps have been removed.
ATTENTION
A cable should not be bent to a radius less than 5.08 cm (2 inches) under full tensile load and 3.048 cm (1.2
inches) with no tensile load.
Tie wraps are not recommended for optical cables because they are easily overtightened.
a.
Orient a cable connector so that the key (the ridge on one side of connector) aligns with the slot in the
transceiver.
b.
Insert the cable into the transceiver until the latching mechanism clicks. For instructions specific to cable
type, refer to the cable manufacturer’s documentation.
c.
Repeat for the remaining transceivers as required.
3.
Check the LEDs to verify that all components are functional.
For information about LED patterns, see the “Operating the FC SAN Module” chapter in the Dell 8/4Gbps FC
SAN Module Hardware Reference Manual.
4.
Verify the correct operation of the FC SAN Module by typing the switchShow command from the workstation.
This command provides information about FC SAN Module and port status.
5.
Verify the correct operation of the FC SAN Module in the fabric by typing the fabricShow CLI command from the
workstation.
6.
Back up the FC SAN Module configuration to an FTP server by typing the configUpload command and following
the prompts.
This command uploads the FC SAN Module configuration to the server, making it available for downloading to a
replacement FC SAN Module if necessary. We recommend backing up the configuration on a regular basis to
ensure that a complete configuration is available for downloading to a replacement FC SAN Module.