A.
Medical Gas Contractor shall coordinate with other trades to ensure timely installations and evade conflicts
and interference.
B.
Work with metal stud partition installer and/or mason to ensure anchors, sleeves and similar items are
provided in sufficient time to avoid delays; chases and openings are properly sized and prepared.
C.
Coordinate with owner to ensure medical gas outlets, whether owner supplied or contractor supplied, in
walls, ceilings and all equipments are provided by the same Medical Gas Equipment Manufacturer (MGEM)
are satisfactory to the owner.
D.
Coordinate with bulk cryogenic gas supplier for installation, connection and verification of bulk gas supply
systems.
E.
Medical Gas Contractor shall supply and install the master alarm system (including the signal wiring). The
electrical contractor shall provide power wiring to each alarm panel. Medical Gas Contractor is responsible
for proper termination, testing and marking of alarm panels. Termination shall be done by or under
the supervision of manufacturer of the alarm panels.
F.
Coordinate with Medical Gas Verifier to deliver a complete, tested medical gas installation ready for owner’s
use.
SUBMITTALS
A.
Furnish the following as one package:
1.
Medical Gas Equipment Manufacturer (MGEM) submittals including at least or at a minimum of the
following:
a.
Complete specifications for the product intended to be installed, dimensional drawings,
and wiring schematics where appropriate.
b.
For Medical Vacuum and WAGD plants include:
(i)
Package drawing indicating package style, dimensions when complete, method of
disassembly and sizes of subsections for rigging and installation.
(ii)
Vacuum System and package capacity expressed with CFM.
(iii)
Lubrication method (if any).
(iv)
Drive detail including adjustment method.
(v)
Motor including frame type, service factor, horsepower, current draw, and RPM.
(vi)
Air filters including type and replacement element.
(vii)
Vacuum regulators including type and manufacturer.
(viii)
Sound pressure in dB(A) when operated within the capacity as stated in the
NFPA 99 Standard.
(ix)
Heat output in BTU for the equipment.
10
- NFPA Triplex RVD Modular Stack Mount NFPA Triplex CCD Modular Stack Mount NFPA Quadruplex RVL Modular Stack Mount NFPA Quadruplex RVD Modular Stack Mount NFPA Quadruplex CCD Modular Stack Mount NFPA Duplex RVL Vertical Tank Mount NFPA Duplex RVL Modular Stack Mount NFPA Duplex RVL Horizontal Tank Mount NFPA Duplex RVD Vertical Tank Mount NFPA Duplex RVD Modular Stack Mount NFPA Duplex RVD Horizontal Tank Mount NFPA Duplex CCD Vertical Tank Mount NFPA Duplex CCD Modular Stack Mount NFPA Duplex CCD Horizontal Tank Mount