Burnham SCG User Manual

Page 66

background image

66

Figure 38: 1 Inch Main Burner fl ame

Figure 39: Pilot Burner Flame

Figure 37: Sequence of Operation

H.

Follow Operating Instructions to place boiler in

operation. See Figure 36.

I.

Sequence of Operation. See Figure 37. If boiler fails

to operate properly, see Troubleshooting Tree in Section
IX: Service.

J.

Check pilot burner fl ame. See Figure 39. Flame

should be steady, medium hard blue enveloping 3/8 to
½ inch of sensing probe.

K.

Check main burner fl ame. See Figures 38. Flame

should have clearly defi ned inner cone with no yellow
tipping. Orange-yellow streaks should not be confused
with true yellow tipping.

L

. Check thermostat operation. Raise and lower

temperature setting to start and stop boiler operation.

M.

Check ignition control module shut-off. Disconnect

pilot lead wires from gas valve. If burners do not
shutdown, determine cause of malfunction. Replace
necessary items and check operation.

N.

Check low water cutoff (if so equipped).

1. Adjust thermostat to highest setting.

2. With boiler operating, open drain valve and slowly

drain boiler.

3. Main burners and pilot burner will extinguish and

blower will stop when water level drops below low
water cutoff probe. Verify limit, thermostat or other
controls have not shut off boiler.

4. Adjust thermostat to lowest setting. Refi ll boiler.