Erection of vertical panels, Panel assembly sequence of a northwind 500 – Bally Refrigerated Boxes 1000 Northwind Blast Chiller User Manual
Page 7
7
3.
Erection of Vertical Panels
3.1 BEFORE ATTEMPTING TO ERECT ANY PREFAB SECTIONS, FAMILIARIZE YOURSELF WITH THE
FOLLOWING CHAPTERS IN THE STANDARD INSTALLATION MANUAL (IM-268-11, Revised
2011):
• Page 4, Section 1
• Page 5, Section 2
Operation of the Bally Speed-Lok
• Page 7, Section 3
Bally Boxes without Floors
3.2 Start by erecting a vertical rear corner
section. When erecting, the holes for the
Speed-Lok wrench must always be on the
left-hand side when facing the interior section.
This is important; crews have installed boxes
upside down.
Panel assembly sequence of a Northwind 500
• The Coil Frame Assembly is installed in the box
before the door is added since the coil is taller than
the opening of the door. You’ll have to slide the
coil out of the way to lock the last corner panel.
• When erecting the front sections of the box, note
that the door latch corner and the door frame
section have a cut out at the top of the panels,
which, when joined, will provide a slot through
which the collar of the control panel will be
inserted.
• Install this cut out corner first, making sure that the
two bottom surfaces in the notch area are perfectly
level.
For the NW 1000 sequence, look in the Appendix.