beautypg.com

Warning – Schwank comfortSchwank - Powder STW-JZ User Manual

Page 8

background image

8

SPW-JZ, STW-JZ(2) / IWP, IW(2) I&O Manual

IM101229

RL: 13A

RD: MAY 2014

VENT END CLEARANCE: Clearances from the vent pipe are determined by local or national
installation codes, but must not be less than 6 inches (15 cm). For ‘unvented’ installation, a
minimum distance of 24 inches (61 cm) is required from the end of heater to a combustible
surface.

In locations used for the storage of combustible materials: Signs
must be posted
specifying the maximum permissible stacking height

to maintain the required clearances from the heater to the combustibles.

The signs must be posted either adjacent to the IR heating system thermostats or in the
absence of such thermostats, in a conspicuous place.

For your convenience a “peel and stick” sign
is provided with this heater. Use a permanent
marker to record the required dimensions on
the sign.

To calculate the value ‘H’: (H = T - C)
 Measure the on site distance between bottom of

the heater and the floor = ‘T’ inches (cm).

 Refer to Table 1 to get the value ‘C’ that corre-

sponds to the model you are installing

 Subtract the clearance below the heater ‘C’ from

T’ to get value ‘H’.

 Enter this value ‘H’ on the sign.

Refer to the information for the heater model

being installed in Figure 1 and Table 1 to get

the values for dimensions ‘S’, ‘F’ and ‘B’.

WARNING

Post this sign as instructed above.

tolerance which may degrade at lower temperatures are protected to prevent

degradation. Examples of low heat tolerance materials include vinyl siding, fabrics,
some plastics, filmy materials, etc.