FLeXSHaFTS/VIBRaTOR HeaDS • OpeRaTIOn anD paRTS manuaL — ReV. #0 (07/16/10) — page 15

OperatiOn

OpeRaTIOn

Before connecting any of the flexible-shafts referenced in

this manual, please read any and all operating instructions

relating to the drive motor associated with the flex-shaft.
Using the wrong drive motor can adversely affect the

performance of the flexshaft/vibrating head. Selecting too

large a flexshaft/vibrating head combination will overload

the motor and cause excessive wear.
1. Hold vibrator head above concrete pour when starting

drive motor. This will prevent the vibrator head from

bouncing on hard surfaces which could damage the

bearings.

2. Keep flexshaft (Figure 6) straight as possible when

operating. Sharp bends increase the load on the core

and drive motor, which will result in early core failure

and possible damage to the drive motor.

Figure 6. Vibrator Head Insertion

3. Completely immerse the vibrator head quickly into

the concrete mix at a verticle rate of about one foot

per second (0.3 meters/second). Vibrate concrete for

about 5 to 15 seconds for wet mixes. For stiff mixes

vibrate 2-3 minutes.

4. Stop vibration of concrete mix when concrete has a

level, glossy surface and there are no breaking air

bubbles.

5. Slowly lift the head out of the mix using an up and

down movement. This slight up and down movement

will close the hole formed by the vibrator.

1-1/2 TIMES AREA

OF INFLUENCE

CORRECT

INCORRECT

FLEX-SHAFT

VIBRATOR HEAD

VIBRATOR HEAD

6. When lifting the head out of the concrete, withdraw

slowly at a rate of about 3 sec./ft. Using this technique

will avoid the re-trapping of air.

7. When near the top of the mix, withdraw the vibrator

quickly.

8. Re-insert vibrator into mix according to the "area

of influence" See Figure 6. Establish a symmertical

overlapping pattern for inserting and removing the

vibrator head.

9. If concrete is poured in layers, allow vibrator to pass

within 3 to 6 inches (76 to 152 mm.) into next layer to

ensure the knitting of the two layers. The complete

bonding of layers will prevent "lift lines" when forms

are removed.

NOTICE

DO nOT use vibrator to move concrete laterally. This

will cause segreation of the concrete. Use a shovel or

similar device to spread the concrete.