ga6HR/6HRS 60 hz gENERATOR • OpERATiON ANd pARTs mANuAl — REv. #0 (08/12/14) — pAgE 27
stopping the Engine (Normal shutdown)
1. Place main circuit breaker (Figure 26) in the
OFF
position.
Figure 26. Main Circuit Breaker (OFF)
2. Place idle control switch (Figure 27) in the
OFF position.
Figure 27. Idle Control switch (OFF)
3. Let engine run at idle with no load for 2-3 minutes.
4. To shut-down the engine, place the generator's
operation switch (Figure 28) in the
OFF position).
Figure 28. Operation Switch (OFF)
ON
OFF
ON
OFF
OFF
ON
OFF
GA6HR
GA6HRS
5. Place engine fuel valve lever (Figure 29) in the
OFF
position.
Figure 29. Engine Fuel Valve Lever (OFF)
6. Remove all loads from the generator.
Emergency shutdown
1. Place operation switch (Figure 30) in the
OFF position.
Figure 30. Operation Switch (Emergency)
OFF
ON
OFF
GA6HR
GA6HRS
SHuTDOWN