A3.0 system configuration and functional checks – MTS Criterion 40 - Installation and Commissioning Plan User Manual
Page 8

Installation and Commissioning Plan
8
MTS Criterion
TM
Series 40
A3.0 SYSTEM
CONFIGURATION AND FUNCTIONAL CHECKS
All required activities are to be completed prior to the start of any training
activity. The system will also be checked to ensure that all components are
operating as intended. Depending on the system configuration, the following
activities will be performed.
Item Description
Performed
On Site
A3.1
Load unit functionality checks:
- Verify
communication
and operation via handset.
Verify handset commands generate proper
crosshead response/motion.
-
Verify Emergency Stop and limits are functional.
-
Verify position control and speed accuracy.
-
Verify signal response and display readings for
position, load, and strain (if applicable).
A3.2
Software functionality checks:
-
Verify proper system parameters in TwDiag_I
program.
-
Verify TEDS (Self-ID) operation of each load cell
and extensometer.
-
Verify system operation in closed loop control.
-
Verify operation of emergency and safety features.
-
Verify the operation of any additional accessories
purchased from MTS.