MK-1280 GAS SAW
MAINTENANCE
MICRO-V BELT INSPECTION, ADJUSTMENT AND REPLACEMENT
NOTE:
When a new belt is installed, it should be inspected and re-tensioned after the
first forty-eight (48) hours of operation.
MICRO-V BELT
Fig. A
Remove Outer Belt Guard
Fig. B
Check Belt tension
Fig. C
To change tension loosen all
four engine mount bolts
Fig. D
Tighten or loosen belt tension
as required
Fig. E
Tighten Engine mount bolts
Fig. F
Replace outer Belt Guard
COOLING FLOW
“Rodding” cooling channels is performed by removing the flow control valve and then inserting a
small wire rod through the cooling channel inlet, on the top of the Blade Guard and directing the rod
out through each of the diamond blade cooling flow outlet ports, located on the underside of the Blade
Guard. The cooling channels should be “rodded” until each of the outlet ports are open and free of
foreign debris.