3 disconnecting from the pc, Disconnecting from the pc, Commissioning – Lenze EPM-H521 User Manual
Page 70

Commissioning
Project transfer to the operating unit
Disconnecting from the PC
5
70
EDBPM-H521 DE/EN/FR 2.0
What to do
A
Switch on the PC and start the »HMI
Designer« planning tool.
B
Switch on supply voltage for operating
unit.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
The device is being initialised.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
C
After initialisation, select the system page.
For this purpose, touch the display at the
corners
top right and bottom left or
top left and bottom right .
The first corner to be touched must not
contain a selectable field.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
The system page appears.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
D
Touch the ”TRAN PAGE” field.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
The transfer page appears.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
E
Touch the field MSP.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
The operating unit is ready for data
reception of the PC.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
F
Transfer the desired project from the »HMI
Designer« into the operating unit.
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
E
HMI Designer - Getting started”
0
1
2
Port
: NET
Driver : CAN Lenze M
Ver
: 1.12
Addr
: NO ADDRESS
Error
: RESET
PROG
ESC
TRAN
PAGE
H521 TRANSFER PAGE
Touch screen BOOT check:
OK
Graphic controller BOOT check:
OK
Graphic controller RAM check:
OK
Main BOOT and RAM check:
WAIT
3
SELECT:
MSP
EXIT
MemoCARD
“PROGRAMMING MODE” is displayed during the download.
G
After download is completed, the operating unit is ready for operation and can exchange data
with the connected nodes by the system bus. The project is stored after disconnection from the
supply voltage.
5.2.3
Disconnecting from the PC
1. Switch off the PC.
2. Switch off the supply voltage for the operating unit.
3. Remove the EPZ-H110 download cable from the operating unit and the PC.
4. Switch on the supply voltage for the operating unit.
The operating unit is now ready for operation.