beautypg.com

6 commissioning, Commissioning – Lenze ECSxK series User Manual

Page 34

background image

Commissioning

6

34

EDBCSXKXXX EN 1.0

6

Commissioning

Before you start
Prior to initial switch-on of the drive system, check the wiring of the capacitor module for

completeness, short-circuit, and earth fault:
ƒ Power connection (X23):

– Polarity of the DC-bus voltage supply via terminals +UG and -UG

ƒ Control connection (X26):

– Wiring adjusted to the signal assignment of the control terminals.

Further information on commissioning the drive system can be obtained from

the documentations for the power supply module and axis module.

Show/Hide Bookmarks