Concrete Slab
At the appropriate location, construct a concrete slab (28 day

compression strength of 3000 psi (200 MPa)) minimum

5 inches thick and 6 inches wider than the enclosure on

all sides. Strengthen slab with No. 6 reinforcing bars (on

12” centers) or 8 ga. steel wire fabric (6” centers). Avoid

placing reinforcement in entrance stub-up area.

Attach unit to slab with 5/16” diameter (minimum) masonry

anchor bolts long enough to retain the unit.

Electrical and Fuel Inlet Locations

A through-slab power cable stub-up is preferred (see above).

If stub-up’s are not used, (A) indicates the recommended

location for punching holes for attaching power conduit. The

fuel inlet connector (B) is shown for reference.

Lifting the Generator

The generator weighs more than 1,700 pounds. Proper tools,

equipment and qualified personnel should be used in all

phases of handling and moving the generator.

WARNING

Hazardous Voltage
Contact with power lines can cause electric

shock or burn.
Lifting Hazard / Heavy Object
Can cause muscle strain or back injury.

DO NOT contact any power lines when using required

lifting/hoisting equipment.
DO NOT lift or move generator without assistance.
Use lifting pipes or straps as described in Lifting the

Generator. The unit may shift during movement, which

can cause injury.
DO NOT lift unit by roof as damage to generator will

occur.


Two 60” lengths of 2” Schedule 40 pipe (B), supplied by the

installer, are required to lift the generator onto cement pad.

Insert pipes through the lifting holes (A) located near the

unit’s base.
Use a spreader bar to ensure that the chains, straps or

cables DO NOT touch the generator’s roof.

B

A

49”

14.25”

94”

78”

38”

9.5”

7”

7.38”

34.25”

10.5”

8”

Power Cable

Stub-in

location

Fuel Inlet

Port

Enclosure

Base

Slab Top VIew

Exhaust

Opening

(shown for

reference)

Anchor bolt

position

(4 places)

B

A

1” Female NPT