Installation, Instructions – Autoquip FREIGHTLIFT FLHC User Manual

Page 65

background image

65



2. All gates or doors accessing the lift must have electrical contacts and mechanical

locks to prevent the lift from operating if a gate is left open. The gate should lock
until the carriage is at the nearest landing. There are many variables that can affect
your installation: the type of gate; the type of door; conditions unique to a specific
site. One (1) to four (4) electrical sensing or signaling devices are supplied with
each gate that incorporates the standard interlock design.


K.
SHAFTWAY BARRIER BAR KIT (for shaftway applications)

Figure 32 illustrates the contents and installation details for the shaftway barrier bar
system supplied for units in 2-level shaftway applications. The barrier bar system is
designed to leave (1) mid and (1) top rail across the door opening at the upper level
when the carriage is called to the lower level.



L.
BACK-STOP KIT (when ordered)

Figure 33 illustrates the contents and installation details for the back-stop kit.
Installer must ensure that the finished distance between the edge of carriage and
the inside of the back-stop panels does not exceed 2 inches.



M.
INSTALLATION WRAP-UP

1. After the unit is completely wired, make all necessary and final adjustments to

ensure proper operation of the lift and its safeties as required by the schematic.


2. Refer to the Inspection Checklist located in the Appendix of this Manual, and

confirm the safe and correct condition of each component/feature listed to ensure
that the lift is ready to be given to the User in proper & safe working condition. This
includes, but is not limited to functionality of gate interlocks, gate status switches, lift
level/status limit switches, and pressure switch.

3. Ensure that the appropriate person signs off on the Warranty Registration Card and

receives one Operation & Service Manual per lift.

4. Install all WARNING SIGNS AND DECALS provided with the unit which may have

been shipped loose for field installation (gate panel, etc.). Refer again to Figure 1.

5. Clean up the area, paint and touch-up as needed.

6. Conduct

Operator

training

before handing off the lift to the customer. Use this

manual as reference for this training & familiarization process.