Installation, Instructions – Autoquip FREIGHTLIFT FLHC User Manual
Page 29
29
THE TOOLS REQUIRED FOR INSTALLATION
Listed below are some of the tools needed to install the FREIGHTLIFT in a professional
and prompt manner. Individual site situations and a basic variation in the types of units
may dictate the need for additional items.
Welding Machine and Equipment
Hack Saw, Sawzall, or
Cutting Torch with Full Tanks
Portable Band Saw
Fire Extinguisher
Drill and Drill Bits
Forklift Extension
Cords
Chain Fall
Sledge Hammer
Come-A-Long
Open or box end wrench
Cables or Hook Chains with 1,000# Cap.
Drift Punch
Disk Grinder
Carpenter’s Square
“C” Clamps (12” opening)
Chalk Line
Socket Set (1/2” drive, sockets to 1 1/8”)
Plumb Bobs
Pinch Bar
4’ Level
Hammer Drill & Bits for 1/4”, 3/8” and
25’ / 100’ Measuring Tapes
1/2” anchors
Broom
The following supplies will also be needed:
*Concrete anchors (16 minimum) sized for the required minimum pullout of the base
floor channels and upper level bracing. Refer to the approval drawing since the size of
the anchors can vary for each installation.
*Concrete anchors for accessories, such as enclosures, approach ramps, etc. (Usually
1/4” diameter anchors and at least 12 anchors, minimum.)
*Shim stock for the floor channel, platform carriage corners, and/or approach ramp (if a
part of this installation)
*Hydraulic oil (see oil recommendations “General Maintenance” section)
*Paint (Autoquip Blue: available in 1 and 5 gallons, as well as spray cans)
*3” x 3” steel angle iron or 4” channel for additional bracing
ALSO - BEFORE YOU BEGIN :
1. Beams are too heavy to lift manually and require lifting equipment. Check for
availability of overhead attachment of chain fall or of fork truck before you start.
2. Before you will be able to complete the installation the unit must be operated,
therefore power to the motor is required. Arrange for power before starting
installation.
INSTALLATION
INSTRUCTIONS