Starting procedure


- Check everything using the check list of sub-section

6.4.

- Switch on the motor.
- Check the pressure gauges at the pressure measuring

points.

- Open the discharge side regulating valve to adjust the

duty point of the pump.

CAUTION

• A fluid quantity of a few cm³ per hour will typically

leave the mechanical seal in the form of vapor, mist or
droplets. If there should be a considerable increase in
the leakage rate after the start-up phase, stop the pump
and check the mechanical seal.

• If a stuffing box is installed, the leakage rate after

start-up should be higher than during operation. After
about 1 hour, tighten the gland nuts gradually until
there is a slight drop leakage.


6.6

Particular information


The following parameters should be monitored during
operation:

- power consumption of the motor
- smoothness of pump operation (no vibration)
- bearing temperature
- leakage

6.7

Stopping procedure


- Close the discharge side regulating valve.
- Switch off the motor.
- Once the pump is at rest, close the shut-off valves of

the feed line and cooling line (if installed).


CAUTION

• If there is danger of freezing, the pump should be

drained down.


• Please note that there will always be some residual

liquid even if the pump is emptied in vertical position.

• Ensure that the pump does not contain any hazardous

substances when it is dismantled to be returned to the
manufacturer's factory.

• Ensure that during prolonged inactivity the pump is

operated for about five minutes every 1 to 3 months.