Task 13: test lan/client connectivity (optional) – AT&T DEFINITY 555-230-223 User Manual
Page 55
Installation
Task 13: Test LAN/Client Connectivity
(Optional)
Task 13 is performed to test the TCP/IP connection to ensure that connectivity
exists between the DEFINITY LAN Gateway and the customer’s LAN, as well as
between the DEFINITY LAN Gateway and a client. This testing should be done
jointly with the customer’s LAN administrator.
NOTE:
Connectivity to the DEFINITY LAN Gateway system from a subscriber PC
is not part of the acceptance testing for this feature. Customers are
responsible for verifying that their LAN is communicating with the
subscriber PCs.
Requirements
Login:
craft
Suggested
Materials:
Configuration diagram (see
Appendix E)
Special
Condition:
The ASAI-Ethernet TCP/IP has
been administered and the
system has been rebooted.
1. The preferred option is to have the customer’s LAN administrator perform
a standard LAN ping test into the DEFINITY LAN Gateway using the
addressing information previously provided in Task 10. If the customer is
unavailable to perform this test, go to step 2.
2. Perform the following steps only if the customer is unavailable for
acceptance testing. (However, step 1 above, Joint Testing, is the
preferred testing method.)
a. Access the DEFINITY LAN Gateway Main Menu. Select
Maintenance
and then
Ping Host
follows.