4.5.3 Final steps while securing the installation
1. Once the installation of the cables and sensor is complete, you must then secure the entire installation
by adding plastic tie-wraps on the cables and the sensor. A sufficient quantity of tie-wraps is supplied
with the kit to ensure the installation of one (1) fastener at every 6’’ (15 cm) of cable.
2. Once all fasteners have been installed, have ready the material required for the protection of the
concrete cables in accordance with the concrete pouring method selected. See section 4.6.
3. Lastly, check the resistance and cable insulation and record these measures on line # 2 of the measure-
ment chart on the electrical panel label.
4.6 Concreting
1. Before the concrete is poured, measure the resistance
and cable insulation and record these values on line #3
of the measurement chart on the electrical panel label.
2. Switch the electrical fault indicator ON BEFORE
any circulation on the concrete cables and BEFORE
the concreting process begins.