beautypg.com

Accu-trans  operating procedures – Vanguard Accu-Trans User Manual

Page 12

background image

Accu-Trans

Operating Procedures

8

4.2

Accu-Trans LCD Contrast Control

To darken the LCD display, press and hold
the “Paper

Contrast” switch for two

seconds; to lighten the LCD display, press
and hold the “Paper

Contrast” switch for

two seconds.

4.3

Accu-Trans Printer Paper Control

To advance the Accu-Trans printer paper,
press and release the “Paper

Contrast”

switch.
To retract the Accu-Trans printer paper,
press and release the “Paper

Contrast”

switch.

5.0 ACCU-TRANS PRINTER PAPER

The Accu-Trans built-in thermal printer uses
2.5-inch wide thermal paper for printing test
results. To maintain the highest quality test-
result printing and to avoid paper jamming,
the use of paper supplied by our factory is
highly recommended. Additional paper can
be ordered from either of the two sources
listed below:

Vanguard Instruments Co, Inc.

1710 Grevillea Court

Ontario, CA 91761
Tel: 909-923-9390

Fax: 909-923-9391

Part Number: TP-3 Paper

OR

BG Instrument Co.

13607 E. Trent Avenue

Spokane, WA 99216

Tel: 509-893-9881

Fax: 509-893-9803

Part Number: TP-3 paper

6.0 OPERATING PROCEDURES
Before using the Accu-Trans for measuring
any resistance, operators should review the
Summary of Step-by-Step Operation of the
Accu-Trans
found in Figure 4.0. Accu-
Trans operations are simple, requiring the
selection of choices from the display menus
and responding to the displayed prompts.
However, first-time operators should review

Figure 1.0 to become familiar with the total
Accu-Trans operation and the logical
branching for various test options. (More
experienced operators may use this figure as
a handy help and reference guide.

WARNING

Do not touch or disconnect any test lead
that is connected to a transformer
terminal while high current is being
conducted during any test. Failure to
heed this warning can result in lethal
electrical shock to personnel and/or
damage to equipment.

6.1

General Procedures

a) Ground Accu-Trans to substation ground
(item 5 in Figure 1.0).
b) Plug Accu-Trans power cable into a
power outlet.
c) Insert current-cable plugs and voltage-
sensing cable plugs into respective control-
panel jacks (index 8 of Figure 1.0). Ensure
that voltage plugs are plugged into jacks that
are adjacent to companion current jacks.

d) Attach test-cable clamps to transformer
terminals of winding that is to be measured
(or if load is not an inductance, simply
attach test leads to opposite terminals of the
resistive load).

e) Turn on Accu-Trans power (item 4 in
Figure 1) by pressing “I” on rocker switch.

f) Observe that after configuration data is
displayed briefly, then the start-up menu
displays (with selection options for “1. RUN
TEST,” “2. SETUP”).