beautypg.com

Site inspection, Pit/ foundation, Scale house – Fairbanks Tundra Series Truck Scale User Manual

Page 22

background image

Section 3: Pre-Installation

12/12

22

51193 Revision 5

3.6. SITE INSPECTION

Before accepting the completed work of the

contractor, check the following points.

3.6.1. Pit/ Foundation

All concrete work

MUST conform to standards set

forth by the

American Concrete Institute Code.

Measure the pit/ foundation dimensions carefully, then compare those figures with

the

Fairbanks Certified Drawings.

If there are ANY discrepancies, contact

the construction contractor IMMEDIATELY. Use Appendix II Foundation

Checklist.

The pit floor must be constructed so that no standing water accumulates.

The approaches must be of correct height and level with the top of the pit wall.

Check for correct pier elevation and for smooth, even tops.

Check that a proper sized conduit is provided through the pit wall, below the frost

line, at the location nearest the scale house and instrumentation.

If AC power is required in the pit, for lighting or for a pump, the line must be in a

separate, 1" conduit, at least 36" from the weight signal cable conduit.

Check that the scale pit ground rods are installed in the correct location and

project through the pit floor to the correct height. The scale pit ground rods must

be driven into the earth at the bottom of the pit and tied to the rebar before the

floor is poured. This assures the easiest installation and deepest possible

penetration.

3.6.2. Scale House

Install the

Surge Voltage Protection Outlet Box (11341).

It is recommended that the Indicator is on a dedicated circuit with a separate

circuit breaker.

The Instrumentation should not be subject to direct sunlight, or in environmental

conditions for which it is not intended.

NOTE:

See

Appendix II

for Foundation Checklist.