beautypg.com

Load cell installation precautions, Load cell handling – Fairbanks Tundra Series Truck Scale User Manual

Page 21

background image

Section 3: Pre-Installation

12/12

21

51193 Revision 5

3.5.2. Load Cell Installation Precautions

Correct installation of the load cells is the most critical factor in fully electronic scale

assembly. Perfect load cell installation will frequently compensate for other

intolerances.

Elevation

The load cell must be installed on piers formed to the specific elevation.

Plumb

Each RC load cell must be installed so that it is plumb, to assure loading through the

direct center axis.

Support

When adjustments are complete, the load cell base plates must be fully supported

before any traffic is allowed on the scale.

Equal Loading

Load Cell shims may be required at one or more cells to ensure equal weight

distribution upon each load cell.

3.5.3. Load Cell Handling

Load cells must be handled with care to avoid being damaged during installation.

Refrain from the following:

Rough handling, which can be avoided with care.

Voltage surges, which can be minimized by surge voltage protection.

Welding currents must be avoided by disconnecting or completely removing the

cells during all welding operations.

Dampness can damage the scale’s electronic components. The cell and/or cable

must not contact standing water.

All load cells must be installed correctly, plumb, level and square.

Overloading the scale.