A. Introduction
The Field Pour module’s installation is much the same as the other models with some
minor variations. The basic procedure is to install the foundation for the scale, install the
base plates, position and level the shoring, install the platform modules with locator tools
in place, pour the deck, cure the concrete, then install the load cells.
B. Concrete
Specifications
C. Shoring
The recommended shoring is made up of the provided 4" x 4" timbers 12 feet long. The
crown of the shoring timbers should be up. The actual dimensions of the timbers will
depend on the distance from the foundation floor to the bottom of the modules. Shims
should be placed under each end and center of the shoring beams to achieve proper
elevation. The shoring timbers should be located equally spaced between the load cells.
50785
20
04/12 Rev. 5
Section 3: Field Pour Installation
SET TOP OF WOOD BEAM AT CORRECT HEIGHT
BELOW TOP OF FOUNDATION END WALL,
BEFORE SETTING PANELS IN PLACE
NOTE: SET SHORING BEAMS AT PROPER
ELEVATION BEFORE SETTING SCALE PANELS.
4” x 4” WOOD BEAM. 1 REQ’D. PER PANEL
(SUPPLIED BY FACTORY)
BLOCK AND/OR SHIM UNDER EACH 4 X 4 AS REQ’D.
(SHIM MAT’L. NOT SUPPLIED WITH SCALE)
WASH SLAB
TOP OF PANEL
ADJUST AS
REQ’D.
SPACE @
HALFWAY POINT
SPACE @
HALFWAY POINT
DETAIL “A”
LOAD CELL
LOCATING TOOL
SEE DETAIL “A”
WOOD BEAM
MODULE
SHIM UNDER EACH
WOOD BEAM AT
ENDS & CENTER.
SECT. #2
SUPPORT EACH
BEAM AT
3 POINTS (TYP.)
SECT. #1
LOAD CELL
LOCATING TOOL
SPACE @
HALFWAY POINT
SHORING DETAILS
50785-3
APPROACH
WALL
FOOTING
Note: Field-Pour scales are poured, formed and cured with locating tools in place. Do
NOT install load cells until cure strength is reached.
• Typically 28-30 days. Use a core sample to confirm this.
Use the Certified Prints for all concrete specifications.