Installing pit frames, continued – Fairbanks Aegis Industrial Mild Steel User Manual

Page 19

background image

Section 4: Installing Accessories

08/12

19

51102 Rev. 7

Installing Pit Frames, Continued

7. Use soft wire and make

two (2) loops

by twisting wire around each 2x4 and

the frame.

8. With the frame supported by the wire and 2x4's, use a level to set the frame flush

with the surrounding floor, level, and at the correct height by twisting or untwisting
the wire.

NOTE:

Use the drawing in

Appendix IV

for measurements, concrete

specifications and amounts.

9. Set into place and secure the conduit for the scale cable into the frame opening.

10. Pour the concrete around and under the frame.

11. Level and smooth it with a hand trowel, as needed.

12. If a drain is required, form the pit to place a slope in the pit floor to the drain.

See

Appendix IV

.

Allow cement to cure to a

minimum of 2000 psi

before cutting the wire.

13. Pull the cable through the conduit before placing the scale platform in the frame.

14. Level the platform before installing the instrumentation.