beautypg.com

Detroit Radiant Products Company LS3 Series User Manual

Page 14

background image

14

LS3

Series

5

Prepare mounting surface, if necessary weld blocks, drill holes (see figure 3.3).

NOTE: The burner control box and radiant tubes should be in straight alignment and level.

6

Fasten beam clamp, screw hook or other type of suspension anchor to hanging point.

7

Attach and close S-hook (P/N: S-Hook) and #1 double-loop chain (P/N: THCS) to anchor. Check that

it is securely attached.

NOTE: Threaded rod and turnbuckles may be used.

8

Attach hangers to chains. Adjust chain lengths until radiant tubing is level and equal weight distribution

is achieved. Chains must be straight up and down. Do not install chains at an angle as this can result
in tube warpage or separation.

Figure 3.3

Mounting the Hangers

3.0

Installation

Hanger Placement and Suspension

7

S-Hook and

#1 Double-Loop Chain

5

Wood Beam

5

Concrete Beam

6

Beam Clamp

6

Screw Hook

6

Screw hook

with Locknut

and Washer

7

Threaded Rod

and Turnbuckle

8

Chain

5

I-Beam

6

Beam Clamp

8

Chain

8

Chain

5

I-Beam