Chapter 6-start up/shut down procedures, Before applying supply air to unit – Magnum Venus Plastech UNIVERSAL PROPORTIONER User Manual
Page 19
UPLS SYSTEM OVERVIEW
UP-XX-XX-XX
MAGNUM VENUS PLASTECH
REV 1.00
APRIL 2010
PAGE 19
CHAPTER 6-Start up/shut down procedures
DAILY START-UP PROCEDURE
BEFORE APPLYING SUPPLY AIR TO UNIT
1. Put on Respirator as specified for spray painting, Protective Clothing, Eye
Protection, and Gloves.
2. Tools and materials are available for start up checks.
3. Ball valve for manifold air supply to unit is off.
4. Incoming airline is ½ inch.
5. Incoming airline is connected to the inlet manifold with no leaks.
6. Main air supply is off.
7. Unit is appropriately grounded.
8. Flush tank has appropriate level of solvent.
9. Making sure there is no pressure on the system, check both fluid section packing
nuts, and tighten as necessary.
10. Packing nut reservoirs have approved lubricant and are filled to the correct level.
11. Dispensing gun packings have been tightened.
12. Recirculation gun packings have been tightened.
13. Accumulators have been charged.
14. Check for any material or solvent leaks on the entire unit.
15. Open ball valve to manifold air supply.
16. Check fluid levels of A&B materials and solvents. Add as needed and inspect
material source for any contaminate accumulation. Set solvent flush pressure
and pressure feed pump pressure if included.