5 Commissioning
Initial commissioning must be done by a qualified
professional.
5.1 Control panel
Z
Control panel instructions
5.2 Check points before commissioning
Hydraulic circuit
- Check that the installation and boiler are adequately filled with
water and correctly irrigated and bled.
- Check that there are no leaks on the hydraulic connections.
Gas circuit
- Check that the appliance is properly set for the type of gas used. If
this is not the case:
- Check the supply pressure.
- Check the pressure at the nozzles.
5.4.6 Pressure setting and marking of calibrated injectors
(page: 27)
5.3 Commissioning procedure
Initial commissioning must be done by a qualified
professional.
1. Check the water pressure in the installation. Top up with more
water if necessary.
2. Open the gas valve.
3. Check that the safety thermostat has not triggered. Remove the
safety thermostat hood and press the reset button with a
screwdriver.
4. Set the On/Off switch to 8.
5. Make the settings on the control panel
Z
Control panel instructions