OPERATING INSTRUCTIONS
 
 
Please refer to system specific mechanical and electrical drawings and schematics for full 
information about the particular unit purchased for this site. 
CONTROL PANEL
 
1. The power switch supplies power to the entire system when turned to “LOCAL” red run Light 
will be lighted. When the power switch is in the “REMOTE” position, the unit is unable to run if a 
remote switch permits operation. Examples of the use of the remote contact would be starting to refill a 
tank on low level and stopping on high level or starting on water flow in a treated line and stopping 
when that water flow ceases. 
2. The pressure switch located in the dilution water line needs to be activated by dilution water pressure
before the polymer pump or Gatlin mixer will operate. If the flow of water is not sufficient to create 
20 psi of back pressure, the system will go into a “standby” mode. If a low water pressure condition is 
sensed, the amber “FAULT” light will come on and the pump and Gatlin will stop. The system will 
automatically restart once water pressure is restored. Maximum static water line pressure is 100 psi. 
 
3. The solenoid valve will open when the system power is “ON”. The polymer pump will also be 
energized but individual speed or stroke control settings may cause it to operate anywhere from 0-100% 
of capacity, i.e., the pump can be turned “OFF” by it’s own control knobs even when the systems power 
is “ON”. 
FLUSH WATER
 
1. Normally, the Polymaster is flushed before shutdown. To flush, turnoff the polymer feed pump or turn 
the stroke speed to “0” using the controls on the face of the pump. Now, only dilution water is flowing 
through the system. Allow the water to run for 5-10 minutes, while the Gatlin is turning, to completely 
flush-out the system. 
 
2. Do not flush the chemical feed pump or pump suction and discharge lines with water as water 
will mix the polymer in the line and may solidify or gel.
 
3. For extended shutdown (more than 3-days) the chemical feed pump head and lines can be filled with 
mineral oil. Simply connect the suction line to a source of mineral oil, or fill the calibration column 
with mineral oil, and allow the unit to run until mineral oil has been drawn completely through the 
suction line, pump head and discharge line up to the Gatlin. Turn off the chemical feed pump as soon as 
these lines are filled with mineral oil and continue to run dilution water through the system for at least 
5-10 minutes before shutting down. 