Newport Brass 24-10 Open Towel Ring User Manual
Open towel ring installation instructions
2001 CARNEGIE AVE
SANTA ANA, CA 92705
©2010 Brasstech, Inc. Newport Brass is a registered trademark of Brasstech, Inc.
www.newportbrass.com
Open Towel Ring
Installation Instructions
Model No. 10-10, 13-10, 15-10, 16-10, 19-10, 22-10, 24-10
Recommended Installation by a Professional Contractor
1. Drill hole in wall at desired location using the appropriate drill size:
· Wood Screw (#6 x 2”) - use: 3/32" Drill
· Toggle Screw (6-32 x 3”) - use: 3/8" Drill
2. Fasten BASE (1) to wall using either WOOD/TOGGLE SCREW (2). For model 26-10, square BASE (1) (not shown) to
be level. (See Fig. 1)
3.Thread ADAPTER (3) into BASE (1). Position SPLINE (4), per the Table below, at the proper height from mounting sur
face. Secure SPLINE (4) into place by tightening SETSCREW (5). (See Fig. 2)
4.Temporarily place POST (6) onto BASE (1) to check alignment. If necessary, loosen lower screw on BASE (1) and adjust.
Retighten screw.
5. Locate the ESCUTCHEON (7) over BASE (1). Place POST (6) over SPLINE (4) and against the ESCUTCHEON (7).
Secure into place by tightening the SETSCREW (5). (See Fig. 3)
Post Height
See Table
Fig. 1
Fig. 2
Fig. 3
(949)417-5207
AMS-10-10 Santa Ana CA 92705 1/13/04
www.brasstech.com
3
5
4
1
7
6
MODEL
10-, 15-
13-, 16-,
19-
22- 24-
POST HT.
2 5/16"
2 1/8"
2 3/16" 2 1/16"