6. Installation
52
PNEG-1094 Farm Grain Bin - 4" Corrugation
Options for 2 Ring Doors
Auger Hood
Inner Door Auger Hood 12' (3.66 m) -
24' (7.32 m) Diameters Only
1. Remove bolts, lock washers and
nuts along each side of large
square opening on the inner
door panel.
2. Position auger shield as shown in
and bolt to underside of
top angle with bolt heads under
shield. Replace bolts, lock
washers and nuts through inner
door panel and auger shield.
3. Attach inner door panel to inner bin
door and outer door panel to the
outer bin door.
Bin Step
4. Attach the left and right sides to the
sides of the bin step using four (4)
5/16" x 3/4" grade 5 hex head bin
bolts and nuts.
5. Center assembled step under bin
door and use it as a template
to field drill the holes in the
side wall sheet on the ridges of
the corrugation.
Figure 6X
Figure 6Y
CAUTION
Improperly unloading grain through door opening may cause grain bin failure.
Unloading directly through the door opening should be limited to grain bins no
larger than 24' (7.32 m) diameter and grain depths no greater than 18' (5.49 m).
Unloading from the door opening should be done only with use of an auger hood
with the auger inserted through the opening all the way to the center of the bin.