Chapter 7: Roof Assembly

Assembling the Temperature Cable Bracket

The temperature cable brackets are installed to the roof rafters and support the temperature cables.

Before You Begin

Determine the correct location of the temperature cable brackets within the structure of the A-frame
Assembly. See

About Temperature Cable Brackets and A-Frame Assemblies, page 84

.

What You Should Know

The A-frame assembly consists of two roof rafters, purlin clips, purlins and possibly X-bracing. The temper-
ature cable brackets should be installed when the A-frames are assembled.

NOTE: The temperature cable bracket must be installed at specific locations, see

About Temperature

Cable Brackets and A-Frame Assemblies, page 84

.

1. Attach a right purlin clip (C), a left purlin clip (D) and a temperature cable bracket (B) to the roof rafter

(A), and install two flange bolts (E) and two flange nuts (F).

NOTE: If no X-bracing is installed, install three flange bolts (E) and three flange nuts (F).

2. After all purlins and X-bracing are installed in the A-frame, tighten all hardware to the recommended

torque specifications. See

Bolt Torque Specifications, page 28

.

Figure 7-9 Installing a temperature cable bracket

A

Roof rafter

D

Left purlin clip (CTR-0489)

B

8 in. temperature cable bracket (CTR-0172)

E

7/16 x 1-1/4 in. flange bolt (S-10250)

C

Right purlin clip (CTR-0490)

F

7/16 in. flange nut (S-10251)

3. Install a quick link (C) to each cable bracket (B) to support the temperature cables.

Pneg-4054A 54 Ft Diameter 40-Series Bin

87