beautypg.com

Chapter 7: roof assembly – Grain Systems Tanks PNEG-4135 User Manual

Page 133

background image

Chapter 7: Roof Assembly

Figure 7-45 Installing the first upper roof panel

C

Upper roof panel (CTR-0337)

E

5/16-18 x 1 flange bolt with sealing washer (S-
10260)

D

Middle roof panel (CTR-0343)

F

5/16 in. flange nut (S-3611)

15.With assistance, position the adjacent upper roof panels (C) overlapping the previous upper roof

panels.

16.Install flange bolts (E) and flange nuts (F) to secure the overlapping panels as shown.

Pneg-4135 135 Ft Diameter 40-Series Bin

133