Installing front and rear anchor plates, Installing a leg stand to the dryer basket corner, Chapter 2: dryer supports – Grain Systems PNEG-546 User Manual
Page 11
Installing Front and Rear Anchor Plates
To secure the dryer, you must install the front and rear anchor plates to the leg stand bottoms, thereby ena-
bling the legs to be anchored to the concrete foundation.
1. Use a flange bolt (C) and a flange nut (D) to attach the rear leg anchor plate (A) to the bottom of the
leg stand (E).
2. Position the front leg anchor plate (B) below the rear leg anchor plate (A), and use two flange bolts
(C) and flange nuts (D) to attach the anchor plate to the front of the leg stand (E).
3. Secure the leg stand (E) to the concrete foundation using concrete anchor bolts (not supplied).
Figure 2-4 Leg anchor plate assembly
Callout
Part
number
Description
A
BLK-10057
Rear leg anchor plate
B
BLK-10058
Front leg anchor plate
C
S-6606
0.3125 in. - 18 X 3/4.75 in. zinc
grade 5 flange bolt
D
S-3611
0.3125 in. – 18 grade 2 flange nut
E
D01–xxxx
For leg stand, refer to
Supporting the Dryer with Leg
Stands, page 9
Installing a Leg Stand to the Dryer Basket Corner
If not using concrete blocks, you must install leg stands to the dryer frame at the dryer basket corners to
support the dryer.
What You Should Know
The additional width of the hitch bracket requires the use of an extra shim to install the legs located at the
dryer frame corners.
To install a leg stand to the dryer basket corner:
1. Remove the two existing bolts and nuts from the dryer frame corner (E and F).
2. Align the holes in leg stand (H) with the holes in the dryer frame corner, and fasten in place using the
bolts and nuts that were previously removed (E and F).
3. Align the top hole in the leg stand with the hole in the basket corner leg (G).
4. Fasten the legs together using bolt (B), washer (C), two shims (A), and nut (D).