Installing the link 1000, Overview of installation steps, Ep 6 on – Xantrex Technology Link 1000 User Manual
Page 19

Installing the Link 1000
11
Installing the Link 1000
Overview of Installation Steps
Complete the installation in this order. Refer to
1. Mount the control panel (
2. Mount the shunt, and cable it to the negative battery
terminal. Cable the load side of the shunt to the negative
bus for DC loads (
3. Connect wires to the Link 1000 terminal block (
4. Connect wires from the terminal block to the shunt and to
the battery’s positive terminal (
5. Install the fuses (
6. Connect the phone cable to the control panel and the
inverter/charger (