Gas piping, Gold cgs gas-fired water boiler — boiler manual, Natural gas – Weil-McLain GOLD CGS 550-110-260/0508 User Manual
Page 25: Propane gas, Connecting gas supply piping to boiler
Part number 550-110-260/0508
25
GOLD CGs Gas-Fired Water Boiler — Boiler Manual
Gas piping
5
26020
Manual main
shutoff gas valve
(when required)
Ground joint union
(when required)
Nipple
Tee
Cap
Table 4
Pipe capacity for 0.60 specifi c gravity natural gas
Natural Gas:
1. Refer
to
Table 4
for pipe length and diameter. Base
on rated boiler input (divide by 1,000 to obtain cubic
feet per hour).
Table 4
is only for gas with
specifi c
gravity 0.60, with a pressure drop through the
gas piping of 0.30” w.c.
For additional gas pipe
sizing information, refer to ANSI Z223.1 (or B149.1
or B149.2 for Canadian installations).
2. Inlet pressure required at gas valve inlet:
•
Maximum: 13” w.c.
•
Minimum: 5” w.c.
•
Manifold gas pressure: 3.5” w.c.
3. Install 100% lockup gas pressure regulator in supply
line
if inlet pressure exceeds 13” w.c.
Adjust for
13” w.c. maximum.
Propane Gas:
1. Contact gas supplier to size pipes, tanks and 100%
lockup gas pressure regulator.
2. Adjust propane supply regulator provided by gas
supplier for 13” w.c. maximum pressure.
3. Inlet pressure required at gas valve inlet:
•
Maximum: 13” w.c.
•
Minimum: 11” w.c.
•
Manifold gas pressure: 10” w.c.
Connecting gas supply piping to boiler
1. Remove jacket front panel and refer to
Figure 14
to pipe gas to boiler.
a.
Install drip leg
at inlet of gas connection to boiler. Where local
utility requires drip leg to be extended to the fl oor, use appropri-
ate length of pipe between cap and tee.
b.
Install ground joint union
for servicing, when required.
c.
Install manual shutoff valve
in gas supply piping outside boiler
jacket when required by local codes or utility requirements.
d.
In Canada
— When using manual main shutoff valve, it
must be
identifi ed
by the installer.
2.
Support piping
with hangers, not by boiler or its accessories.
3.
Purge all air
from gas supply piping.
4. Before placing boiler in operation,
check boiler and its gas connection
for leaks
.
a.
Close manual main shutoff valve
during any pressure testing at
less than 13” w.c.
b.
Disconnect boiler and gas valve from gas supply piping
dur-
ing any pressure testing greater than 13” w.c.
Do not check for gas leaks with an open fl ame
— use bubble test. Failure to use bubble test or check
for gas leaks can cause severe personal injury, death or
substantial property damage.
5.
Use pipe dope compatible with propane gases.
Apply sparingly
only to male threads of pipe joints so that pipe dope does not block gas
fl ow.
Failure to apply pipe dope
as detailed above can result
in severe personal injury, death or substantial property
damage.
Figure 14
Gas supply piping
Gas pipe
length
(feet)
Capacity of pipe for pipe size of:
(Capacity in cubic feet gas per hour)
½"
¾"
1"
1¼"
1½"
10
132
278
520
1050
1600
20
92
190
350
730
1100
30
73
152
285
590
860
40
63
130
245
500
760
50
56
115
215
440
670
75
45
93
175
360
545
100
38
79
150
305
460
150
31
64
120
250
380