1

Installation of drawer assembly
and front access panel and back
base channel

(Factory installed on PEG boilers - follow

steps 2 and 3)

1. The drawer assembly consists of the burner drawer,

main burners, gas manifold, pilot burner, etc. See
Figures 6, 7 and 8 for installation.

2. Check for proper orifice sizing from chart below.

Proper orifices must be used. Failure to do
so will cause severe personal injury, death
or substantial property damage.

3. Level and straighten burners.

Burners must be properly seated in slots in
back burner support with openings facing
up. Gas orifices must inject down center of
burner. Failure to properly seat burners
will result in severe personal injury, death
or substantial property damage.

4. Install front access panel and back base channel. See

Figure 9.

5. Install rollout thermal fuse element with wire

terminals facing up on front access panel of EG 30-75
boilers only as shown in Figure 9. Wire per Control
Supplement.

Figure 5

Front and back base panels

Figure 9

Access panel

Figure 8

Burner drawer installation

Figure 7

Pilot burner location

Figure 6

Burner drawer assembly