Tower installation – Powerware 9125 User Manual
Page 22
INSTALLATION
EATON Powerware
®
9125 Two-in-One EBM (700–2000 VA) User’s Guide
S 05146489 Rev D www.powerware.com
18
Tower Installation
The UPS and EBMs must be stabilized with joining brackets.
1.
Carefully position the cabinets upright with the air vents at the top
(see Figure 4).
Air Vents
Figure 4. Tower UPS with EBMs
2.
Remove the adjacent corner screws from the rear panels as shown
in Figure 5 to install the joining brackets. Discard the screws.
3.
Align each joining bracket with the screw holes and secure with the
screws provided in the accessory kit.
4.
If installing additional EBMs, repeat Steps 2 and 3 for each cabinet.
Joining Bracket
Joining Bracket
EBM
UPS
Figure 5. Installing the Joining Brackets