3 - connecting the ird ground wire, 4 - installing the switchplate, 3 connecting the ird ground wire – KVH Industries TracVision C3 User Manual
Page 30: 4 installing the switchplate
2-12
A Guide to TracVision C3
2.3.3 Connecting the IRD Ground Wire
A grounding wire (Cable #32-0583-50) has been provided to
connect your IRD to a suitable ground and protect the system.
Attach the grounding wire to any suitable screw on the rear
panel of the IRD with a good contact with the IRD chassis. The
other end should be connected to a suitable ground, ideally the
ground connector on the switchplate (see
2.3.4 Installing the Switchplate
After completing the switchplate wiring process, you must install
the switchplate itself. This process, detailed in the following
steps, is illustrated in Figure 2-16.
1. Fit the switchplate assembly and support frame
into the panel cutout made in Step 2 of
“Connecting System Components,”
mounting surface.
2. Drill out four
5
⁄
32
" (4 mm) holes in the countersunk
settings in the switchplate support frame.
3. Drill four
3
⁄
32
" (2.5 mm) holes in the mounting
surface using the countersunk holes in the support
frame as the template. Secure the support frame
and switchplate assembly to the mounting surface
using four #6 self-cutting screws.
4. Snap the front cover into place to cover the screws
and support frame.
5. Reinstall the vessel fuse removed in Step 1 of
Section 2.3.2, “Connecting to Vessel Power.”
3.82"
(97 mm)
2.36"
(60 mm) 2.05"
(52 mm)
3.19"
(81 mm)
A. Panel Cutout
B. Support Frame
C. Front Cover
5
/
32
"
(4 mm)
3
/
32
"
(2.5 mm)
Figure 2-16
Mounting the Switchplate
Support Frame and Front Cover
Before securing the switchplate to
the mounting surface, be sure to
strain-relieve the wires connecting
to the switchplate connectors.
Several tie-wraps have been
provided to aid in strain-relieving
the wires.